The NCA has issued a progress report regarding the restoration of data services affected by the damaged submarine cables on March 14, 2024.
Collaborating with SAT-3, ACE, WACS, and MainOne, the NCA has been informed that two repair vessels have been deployed for the necessary repairs.
Repair Timelines:
SAT-3: Their repair vessel departed from Cape Town, South Africa, on March 19, 2024, and is expected to reach the fault area by March 29, 2024.
Repair works will commence immediately, with completion anticipated by the second week of April, 2024.
MainOne, WACS, and ACE: Collaborating, these providers commissioned a joint repair vessel, which set sail from London, UK, on March 24, 2024.
It is scheduled to reach its first point of call by April 8, 2024.
The tentative timelines for restoration are as follows:
- ACE: Expected completion by April 17, 2024
- WACS: Expected completion by April 28, 2024
- MainOne: Expected completion by May 9, 2024
The NCA emphasised that these dates are tentative and subject to change, promising further updates in case of new developments.
Information from MyjoyOnline was added to this report.